Construction Issues - Traffic, Roads and Windfarm Infrastructure
On this page
Countryside Damage Preparing the site Transport Roads Electricity Substations Pylons Cables Within the Windfarm Construction
More Environment Impact Environmental Impact
Countryside Damage

Apart from excavations for the pylon bases and huge concrete bases, the infrastructure of windfarms requires roads, cables, electricty pylons to take the elctricity away and substations.
See the photo gallery from the web site of Cefn Croes in Wales

for pictures of countryside dammage and to see the size of the excavations
Preparing the Site



These photographs were taken during November 2009, and show some of the proposed locations for wind turbines at Ingram Grange.

Most people accept that our climate is changing, and that we are experiencing more frequent spells of very wet weather.

What will need to be done to make sites such as these suitable for wind turbines and an electricity sub-station?







Transport & Construction Traffic


This photograph shows components of the turbines for Scout Moor wind farm being transported. These turbines are 100 metres tall. 10 metres shorter than the ones proposed for Appleton Wiske.

The developers of the proposed site at Bullamoor of 4 turbines of similar sizes to those proposed at Appleton Wiske estimate, 17,000 vehicle movements over a 9 month period.

That could mean over 38,000 movements in our area to build the Ingram Grange 9 turbine site.

Will these monsters be able to use the existing roads?

Damage to local roads

This photo show the turbine blades for Scout Moor being transported

  • In some cases, the developers "straighten" bends to accommodate the transportation of the enormous components
  • Sometimes trees have to be cut down

  • Electricity substations

    A substation will need to be built to transform the electricity produced by the turbines to a voltage which can be transported by either underground cables or pylons
    Pylons

    The electricity needs to be "carried" away and that might mean huge pylons.
    Cable laying

    It will be necessary to lay cables from the turbines to the electricity substation.
    Roads within the wind farm

    For access a network of roads will need to be built within the windfarm.
    Construction Equipment

    Heavy construction equipment will need to brought in.

    Appleton Wiske sponsors NHWAG